Exceptional dates

Use an exceptional date for a one-off change, such as a compensatory working Saturday or an unplanned closure, without editing week offs or holiday calendars.

Steps​

  1. Go to Attendance configuration → Exceptional dates and select Add Exceptional Date.
  2. Choose the Date and the Exceptional day type:
TypeEffect
Working day as holidayA normal working day becomes a holiday. Choose the Holiday type.
Working day as week offA normal working day becomes a week off.
Holiday or week off as working dayA holiday or week off becomes a normal working day.
  1. Choose who it applies to, by Location, Designation, Cost Center, Grade, or Selected Employees.
  2. Enter a Reason, leave Active on, and save.

After saving​

Attendance for the affected employees and date is processed with the new day type. If the date is in the past, reprocess attendance for that date.